City Fibre work across Cambridge


Read on for details of when the works will happen, and an FAQ on the works.

The latest schedule, which will be refreshed once a week here, is:  20200211_CityFIbreCambridge.csv

(we had a Public meeting at The Waterman pub, rear shed, 1800-2000 on 2020-01-30 (6pm-8pm on the 30th January) with representatives from City Fibre present, and potentially could organise another if needed). 

 

Area Schedule

The schedule for works covers the following areas on the map lower down a "PN"is a "Primary Node" which covers about 400 properties.

PN Start Finish
PN 50 Dec 2019 Mar 2020
PN 118 Jan 2020 Mar 2020
PN 29 Jan 2020 Apr 2020
PN 42 Jan 2020 Apr 2020
PN 47 Jan 2020 May 2020
PN 133 Feb 2020 May 2020
PN 144 Feb 2020 June 2020

These map onto the areas shown below:

718px-Sf2.jpg

Detailed schedule

This will be regularly updated as we have information from City Fibre: works schedule 

 

FAQ notes

These are not exhaustive but are examples of what is and isn't allowed.

They are not permitted to leave any more that 40m of trench open and barriered overnight in any one street.

There should be work people available to facilitate access to houses at all times.

Replanting of eg verge damage is scheduled for March onwards. Under the New Roads and Street Works Act 1991 they work is subject to the standard two year guarantee; with a minimum of the statutory two reinstatement inspections by the County Council being made during this period; 3-6 months after completion and at 21 months from completion, just before the two year guarantee period.  

The category of work is defined as 3 days for minor works, 10 days for standard works, then anything over 10 days become  major

Resources

  • Dedicated enforcement officer for works, paid for by City Fibre, employed by County